All spent fuel was unloading from SFP-3 at Fukushima Daiichi NPP

AtomInfo.Ru, PUBLISHED 01.03.2021

Work on unloading fuel from the spent fuel pool of Unit No. 3 of the Fukushima Daiichi nuclear power plant (Japan) has been completed.

In total, 52 fresh assemblies and 514 spent assemblies were unloaded.

Work on unloading the pool has been started in April 2019. The last batch of six fuel assemblies was unloaded on February 28, 2021.

Thus, to date, the spent fuel pools of two units (the third and the fourth) have been unloaded.

Work on unloading the pools of the units No. 1/2 will begin in 2024 or later.

Topics: NPP Fukushima Daiichi


Other news:

Rosatom will manufacture unique equipment for the BREST-OD-300 power unit

Installation of the main equipment should be completed in 2025.

Power unit 1 of Belarus NPP started operation at 100% capacity

It is the main event at the stage of trial operation.

Akkuyu Nuclear JSC Obtains the Construction License of Akkuyu NPP Unit 3

The license application package was submitted to the Nuclear Regulatory Authority (NRA) on March 28, 2019.


Hero of the day

Nuclear fuel elements for Chinese HTGR shipped

Nuclear fuel elements for Chinese HTGR shipped

The shipment of 78,000 spherical fuel elements to the demonstration plant is part of an initial delivery of 870,000 spherical fuel elements, which are expected to be put into the reactor in April.



INTERVIEW

Vladimir Kriventsev

Vladimir Kriventsev
The International Atomic Energy Agency brings together the fast reactor and related fuel cycle community and countries and the wider public interested in these technologies by organising the International Conference on Fast Reactors and Related Fuel Cycles: Sustainable Clean Energy for the Future or FR21.


OPINION

Victor Murogov

Victor Murogov
This critical analysis of the history, state, and prospects of development of modern nuclear technologies shows that nuclear energy market has practically monopolized the design and construction of only one type of reactors (95% of NPPs under construction use pressurized water reactors), which necessitates training of focused specialists involved in the construction and operation of those nuclear power plants.


Search: