Fuel removal from SFP-3 at Fukushima-1 completed

TEPCO, PUBLISHED 06.03.2021

The removal of fuel from the Unit 3 spent fuel pool commenced on April 15, 2019 with the objective of completing it during FY2020 in accordance with the Mid-and-Long-term Roadmap.

February 28 at 1:59 PM, at the end of the 84th fuel removal session, the final six fuel assemblies from the spent fuel pool were removed from their transport containers and placed into the fuel rack in the common pool thereby completing this project.

The removal of fuel from the Unit 3 spent fuel pool consisted of a series of preparatory tasks that were completed one by one, such as the removal of rubble from, and decontamination of, the uppermost floors of the reactor building, the construction of a fuel removal cover, and the installation of a fuel handling machine.

Since all of these tasks had to be performed in a high-dose environment, remotely operated equipment was used to remove debris while removing fuel.

This was the first time such methods were attempted and there were various problems that had to be overcome. However, TEPCO worked as one with contractors to continuously make improvements that resulted in the safe culmination of this task today.

The knowledge and lessons learned from this endeavor will be leveraged during the upcoming fuel removal from the Unit 1 and Unit 2 spent fuel pools as we continue to steadily move forward with decommissioning while prioritizing safety.

Topics: NPP Fukushima Daiichi


Other news:

TVEL Elemash Machine-building plant launches new manufacturing site for CFR-600 fabrication

The dummy fuel bundles for CFR-600 are already manufactured for testing.

All spent fuel was unloading from SFP-3 at Fukushima Daiichi NPP

SFP-3 and SFP-4 are free of fuel now.

Rosatom will manufacture unique equipment for the BREST-OD-300 power unit

Installation of the main equipment should be completed in 2025.

Hero of the day

Nuclear fuel elements for Chinese HTGR shipped

Nuclear fuel elements for Chinese HTGR shipped

The shipment of 78,000 spherical fuel elements to the demonstration plant is part of an initial delivery of 870,000 spherical fuel elements, which are expected to be put into the reactor in April.



INTERVIEW

Vladimir Kriventsev

Vladimir Kriventsev
The International Atomic Energy Agency brings together the fast reactor and related fuel cycle community and countries and the wider public interested in these technologies by organising the International Conference on Fast Reactors and Related Fuel Cycles: Sustainable Clean Energy for the Future or FR21.


OPINION

Victor Murogov

Victor Murogov
This critical analysis of the history, state, and prospects of development of modern nuclear technologies shows that nuclear energy market has practically monopolized the design and construction of only one type of reactors (95% of NPPs under construction use pressurized water reactors), which necessitates training of focused specialists involved in the construction and operation of those nuclear power plants.


Search: