Installation of steam generators has been completed at Kursk NPP-2 power unit 1

Communications Division of ROSATOM Engineering Division, PUBLISHED 07.06.2022

In the reactor building of Kursk NPP-2 power unit 1 (with the ROSATOM's Engineering Division being its general designer and general contractor), the last of the four steam generators has been installed in the design position within the established time frames.

The installation of steam generators was carried out by Kursk Branch of Energospetsmontazh JSC.

"The installation of steam generators is an important stage in the creation of the reactor primary circuit system. It opens up a possibility to start the installation of the reactor vessel of the first power unit in the nearest future, and in the prospect - the installation of the main coolant pipeline," said Oleg Shperle, ASE JSC Vice President, Director for Kursk NPP Construction Project.

The steam generator is a heat exchanger with a length of 15 meters and a weight of 355 tons. It is designed to produce steam supplied to a turbo generator to convert thermal power into electric power.

Topics: Kursk NPP, Russia


Other news:

Russian specialists present reports at IAEA Conference on Fast Reactors

A total of 70 reports by Russian participants were presented at the conference.

Specialists of SSC RIAR have successfully completed the modernization of the VK-50 reactor

This is the first and only operating pressurized boiling reactor with natural coolant circulation in the country.

Ghana will decide on the site before the end of the year

Four candidate sites are currently being explored.


Hero of the day

First Concrete laid at Xudapu NPP Power Unit 4 in China

First Concrete laid at Xudapu NPP Power Unit 4 in China

First concrete ceremony has taken place at Xudapu NPP Unit 4 constructed under the Russian VVER-1200 design. The construction has reached its active phase. Xudapu NPP Unit 3 is also in the active stage of construction.



INTERVIEW

FR22 concluded its work

FR22 concluded its work
The International Conference on Fast Reactors and Related Fuel Cycles: Sustainable Clean Energy for the Future (FR22) concluded its work at the IAEA headquarters in Vienna.


OPINION

AtomInfo.Ru

AtomInfo.Ru
Russia has adopted a strategy providing for the formation of two-component nuclear power with fast and thermal reactors. And this means that the VVER technology will remain in our country.


Search: