Sixth unit of the Leningrad NPP will be stopped for planned overhaul

AtomInfo.Ru, PUBLISHED 09.02.2025

The power unit No. 6 of the Leningrad NPP, in accordance with the schedule of the Rosenergoatom concern, will be scheduled to be disconnected from the grid from February 8, 2025 for major repairs, which will be completed in the spring of this year.

This is reported on the website of Rosenergoatom.

The program includes more than 500 works, the execution of which will ensure reliable and safe operation of the unit in the next inter-repair period.

More than 1.5 thousand people will be involved in the repair - the staff of the nuclear power plant and the staff of the specialized repair organization of JSC Atomenergoremont, as well as chief engineers of equipment manufacturers.

A team of specialists will carry out a large-scale audit and maintenance of reactor and turbine equipment, safety systems, diesel generator sets, lifting mechanisms, etc., if necessary, specialists will replace individual components and parts.

They will also carry out work with nuclear fuel and check the sealed shell of the reactor building for integrity and density.

Also, as part of the ongoing repair campaign at the LNPP power unit No. 6, the turbine generator will be upgraded with stator replacement, the individual control systems of the power unit and the passive heat removal system from steam generators will be upgraded.

Topics: NPP, Russia, Leningrad NPP


Other news:

417 nuclear units are operating in the world, 62 units are under construction

Since the beginning of 2024 six new units have been connected to the grid.

416 nuclear units are operating in the world, 63 units are under construction

The construction was started on nine new units since the beginning of 2024.

Russian government has approved the general scheme for the placement of electric power facilities until 2042

38 nuclear power units with a total capacity of 29.3 GW are scheduled to be commissioned by 2042.


Hero of the day

National flag of Russian Federation hoisted on Yakutia nuclear icebreaker

National flag of Russian Federation hoisted on Yakutia nuclear icebreaker

Yakutia is the fourth icebreaker actually built under Project 22220. Its service life is 40 years. As is the tradition, the icebreaker is named after a region adjacent to the Northern Sea Route.



INTERVIEW

Rosatom

Rosatom
Pietro Barabaschi held a meeting with the management of the Institute and saw around the facilities for high-tech components manufacturing of the future plant.


OPINION

CNNC

CNNC
the 400-ton toroidal field coil TF08 of the ITER was successfully hoisted onto the sub-assembly of the Vacuum Vessel Module 1, marking another milestone in the sector module sub-assembly (SMSA).


Search: