Major milestone achieved in the ITER

CNNC, PUBLISHED 07.04.2025

On March 28, the International Thermonuclear Experimental Reactor Organization (IO) held a grand ceremony to officially announce the completion of the SSAT (sector-sub assembly tool) work of Vacuum Vessel Sector Module 7, meeting the conditions for its installation into the Tokamak pit. This milestone signifies major progress in the core installation work undertaken by the consortium of China Nuclear Power Engineering (CNPE) Co., Ltd, a subsidiary of China National Nuclear Corporation (CNNC), and lays a solid foundation for advancing the ITER project on schedule. ITER Director-General Pietro Barabaschi highlighted that reaching this milestone once again demonstrates the dedication, ingenuity, and professionalism of the project team.

On February 6, 2024, the consortium of CNPE won the contract for assembling the vacuum vessel modules for the Tokamak of the ITER, marking Chinese team as the sole contractor for the installation of ITER's most critical equipment. On March 28, 2024, the sector modules sub-assembly (SMSA) project kick-off meeting was held, with full-scale construction commencing on-site. Faced with world-class challenges, such as the precise assembly of the vacuum vessel modules and the integration of multi-national standards, the consortium swiftly established a collaborative mechanism involving experts from China, France, and Italy. By September 18, 2024, the team successfully initiated the relocation of Module 7 to the ITER site.

With the lifting and positioning of Module 7 brought forward to April 15, 2025, the consortium faced the challenge of a compressed 41-day timeline. To meet the rescheduling challenge, the team ramped up efforts by optimizing installation procedures and establishing a rapid response mechanism. Despite challenges such as manpower shortages, the consortium maintained strict adherence to quality and safety standards, and successfully met the lifting conditions on March 28.

As the core of the Tokamak, the precise installation of nine sector modules of the vacuum vessel directly impacts plasma confinement performance. Module 7, being the first core component to enter the lifting phase, has attracted significant attention. The IO leader stated, "This breakthrough not only validates the Chinese team's system integration capabilities in ultra-precision nuclear engineering but also sets the foundation for a standardized operational model for subsequent module installations."

Topics: Fusion, ITER, China


Other news:

Leaders of Global Nuclear Industry to meet at World Atomic Week in Moscow

World Atomic Week international forum will take place From September 26 to September 30, 2025.

Russia and the IAEA hold another round of Interdepartmental consultations in Moscow

The parties reaffirmed their commitment to continue contacts on a regular basis.

417 nuclear units are operating in the world, 62 units are under construction

Since the beginning of 2024 six new units have been connected to the grid.


Hero of the day

Russia and Myanmar signed an intergovernmental agreement for the construction of a small modular reactor

Russia and Myanmar signed an intergovernmental agreement for the construction of a small modular reactor

The intergovernmental agreement regulates the conditions and main directions of interaction between the parties within the framework of implementation of the 110 MW SMR project with the possibility of further expansion up to 330 MW.



INTERVIEW

Yuriy Chernichuk

Yuriy Chernichuk
What does management mean? Financial flows, personnel policy, and investment policy can be managed. Technically, the plants will be managed by personnel who are trained in this.


OPINION

Rosatom

Rosatom
This is not just the start of a new unit construction at the Leningrad NPP-2. This is another step towards the major national goal of increasing the share of peaceful nuclear energy in the national energy mix.


Search: